Routine Maintenance Of Emali/mulala Ward Access Roads

Completed GoMC-PMTS-2024-8448
Project Description

This budget line entails both contracted (Ksh 2,000,000) and in house works (Ksh 2,000,000)

Scope for Contracted works include 6km road opening amd 12km road grading along Emali kwa kamba - kongo -kwa kite road (2.9Kms) Kwa amini - kwa kirunja - kwa ndeke (6Kms), Kativani kwa kombo - katisaa - Mwasangombe(4.2Kms)

Inhouse (MTF)

Opening  and grading of Welfare-Katisaa-Mwasang’ombe road

• Opening and grading of Kwa Kombo-Kativani-Katisaa road

•  Opening and grading of Kwa Kamba-Kongo- Kite road

•  Opening and grading of Kwa Amin -Kwa Kilungya-Kwa Maima-Kwa Ndeke road


Budget & Expenditure
Approved
KES 4.00M
Contract
KES 0.00
Spent
KES 1.84M
Utilisation
46.1%
Budget Utilisation
Components (1)
Component Budget Expenditure Status
MTF - Emali Mulala KES 2.00M KES 0.00 Ongoing
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8448
  • WardEmali/Mulala
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 10 Oct 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 20 Nov 2024
Awarded
Phase Two · 25 Nov 2024
Site Handover
Phase Three · 25 Nov 2024
Not Started
Phase Three · 25 Nov 2024
Ongoing
Phase Three · 02 Dec 2024
Completed
Phase Three · 06 Mar 2025