Construction Of Muangeni Drift

Completed GoMC-PMTS-2024-4843
Project Description

2.7kms heavy Bush clearing,  2.7kms heavy grading, 1km Gravelling ,installation of  16m  (600mm dia.) Culverts,construction of  20No. Gabions, 40m x6m RC non-vented drift slab, 30mx6m wide ridding surface, and 695cm of Catch water drains

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 0.00
Spent
KES 5.91M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4843
  • WardKikumbulyu North
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Oct 2024
Approved Requisition
Phase Two · 18 Nov 2024
Floated
Phase Two · 04 Dec 2024
Awarded
Phase Two · 06 Feb 2025
Site Handover
Phase Three · 10 Feb 2025
Not Started
Phase Three · 10 Feb 2025
Ongoing
Phase Three · 10 Feb 2025
Completed
Phase Three · 04 Jun 2025