Infrastructure Improvement For Makueni Referral Hospital - Mortuary, Gate And Medical Equipment

Ongoing Flagship GoMC-PMTS-2024-1619
Budget & Expenditure
Approved
KES 21.47M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Components (8)
Component Budget Expenditure Status
supply of icu bed KES 17.37M KES 0.00 Ongoing
supply of adult and paediatric ventilator machine KES 17.37M KES 0.00 Ongoing
supply of dual headed teaching Microsoft KES 17.37M KES 0.00 Ongoing
supply of otoscopy,larygoscopy and tonometer machine KES 17.37M KES 0.00 Ongoing
SUPPLY AND DELIVERY OF CTG MACHINE AND FETAL DOPPLER KES 17.37M KES 0.00 Ongoing
SUPPLY AND DELIVERLY OF 2 DIALYSIS MACHINE KES 17.37M KES 0.00 Ongoing
SUPPY AND DELIVERY OF VITAL SIGNS MONITORS, PULSE OXIMETERS, CRASH CARTS AND PORTABLE LIGHTS KES 17.37M KES 0.00 Ongoing
SUPPLY AND DELIVERLY OF NEW BORN UNIT KES 17.37M KES 0.00 Ongoing
Citizen Feedback
Bright Wekesa 02 Apr 2026
Infrastructure Improvement For Makueni Referral Hospital - Mortuary, Gate And Medical Equipment

Please Update Me On The Current Status Of This Project And The Projected Completion Dates

Official Response:

Thank you for your inquiry. Kindly note that the project is currently ongoing. The Government remains committed to its completion and it is expected to be finalized as planned.

Mutuku Muema 30 Mar 2026
Infrastructure Improvement For Makueni Referral Hospital - Mortuary, Gate And Medical Equipment

How Will The Community Access The Morgue From Hospital Gate

Official Response:

The facility will be accessible to all members of the public requiring its services, similar to the Makueni Referral Hospital.

Project Details
  • RefGoMC-PMTS-2024-1619
  • WardWote/Nziu
  • Sub-CountyMakueni
  • DepartmentDepartment of Health Services
  • DirectoratePreventive and Promotive Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryFlagship
Timeline
Cabinet Paper Approved
Phase One · 29 Oct 2024
Approved Requisition
Phase Two · 30 Oct 2024
Floated
Phase Two · 06 Dec 2024
Awarded
Phase Two · 31 Jan 2025
Site Handover
Phase Three · 01 Feb 2025
Not Started
Phase Three · 01 Feb 2025
Ongoing
Phase Three · 03 Feb 2025