Kathonzweni Dairy

Completed GoMC-PMTS-2024-4894
Project Description

water connection(piping contract terminated ) payment of electricity bills. procurement of pastueriser and  water purification & softening machine advertised.

Budget & Expenditure
Approved
KES 9.50M
Contract
KES 2.54M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4894
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateLivestock and Fisheries Development
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start28 Jun 2023
  • End28 Sep 2023
Timeline
Cabinet Paper Approved
Phase One · 01 Dec 2023
Approved Requisition
Phase Two · 19 Feb 2024
Floated
Phase Two · 24 Feb 2024
Awarded
Phase Two · 14 Jun 2023
Site Handover
Phase Three · 28 Jun 2023
Not Started
Phase Two · 28 Jun 2023
Ongoing
Phase Three · 28 Jun 2023
Completed
Phase Three · 11 Mar 2024