Construction Of Concrete Slab 30m Long Along Kavani Kituluku Dispensary Road

Completed GoMC-PMTS-2024-5297
Project Description

Construction of 30M drift and 150cm catchwater drain

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 1.42M
Spent
KES 1.42M
Utilisation
94.6%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5297
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start12 Nov 2024
  • End30 Jan 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 23 Sep 2024
Floated
Phase Two · 08 Nov 2024
Awarded
Phase Two · 12 Nov 2024
Site Handover
Phase Three · 12 Nov 2024
Not Started
Phase Two · 12 Nov 2024
Ongoing
Phase Three · 18 Nov 2024
Completed
Phase Three · 17 Jan 2025