Road Improvement Programme Along Kilungu – Kimandeni Road

Completed GoMC-PMTS-2024-8906
Project Description

Road improvement programme through 1.5kms road grading- 0.5Kms, Spot Gravelling , Gabions - 25No., catch water drains - 150cm along Kilungu – Kimandeni Road

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 1.46M
Spent
KES 1.46M
Utilisation
97.6%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8906
  • WardKilungu
  • Sub-CountyKaiti
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start13 Nov 2024
  • End30 Jan 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 23 Sep 2024
Floated
Phase Two · 15 Oct 2024
Awarded
Phase Two · 12 Nov 2024
Site Handover
Phase Three · 13 Nov 2024
Not Started
Phase Two · 13 Nov 2024
Ongoing
Phase Three · 14 Nov 2024
Completed
Phase Three · 14 Feb 2025