Road Improvement Programme along Kitituni -Nyaani road

Completed GoMC-PMTS-2024-9119
Project Description

0.5kms Spot Gravelling,installation of 8m culvert, 50 No. Gabions and 200cm catch water drains

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 1.42M
Spent
KES 1.42M
Utilisation
94.8%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9119
  • WardKilungu
  • Sub-CountyKaiti
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start19 Feb 2025
  • End19 May 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Sep 2024
Approved Requisition
Phase Two · 19 Nov 2024
Floated
Phase Two · 14 Jan 2025
Awarded
Phase Two · 12 Feb 2025
Site Handover
Phase Three · 19 Feb 2025
Not Started
Phase Three · 19 Feb 2025
Ongoing
Phase Three · 19 Feb 2025
Completed
Phase Three · 14 Feb 2025