Thange Ecde

Completed GoMC-PMTS-2024-7131
Project Description

Construction of 1no. ECDE Classrooms with an office; Electrical Works; Shelving to the stores;1No. Wooden Desks; 1No. Wooden Arm Chairs; Water harvesting goods (10,000Ltrs Water Tank); Play equipment - 4 piece set (double swing, slide, climbing frame and double see-saw); Display soft Pin board, White Board & Mark Pens; Branding, Publicity and Signwriting; 20 Kiddy chairs and 10 Kiddy table

Budget & Expenditure
Approved
KES 2.10M
Contract
KES 1.98M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7131
  • WardThange
  • Sub-CountyKibwezi East
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start07 Jan 2025
  • End07 Jun 2025
Timeline
Cabinet Paper Approved
Phase One · 05 Sep 2024
Approved Requisition
Phase Two · 16 Sep 2024
Floated
Phase Two · 02 Dec 2024
Awarded
Phase Two · 07 Jan 2025
Site Handover
Phase Three · 16 Jan 2025
Not Started
Phase Two · 16 Jan 2025
Ongoing
Phase Three · 05 Feb 2025
Completed
Phase Three · 03 Apr 2025