Iiani Ecde

Completed GoMC-PMTS-2024-1413
Project Description

Construction of 2no. ECDE Classrooms with an office,3-Door Pit Latrine with Urinal,Electrical Works,Shelving to the stores, 2No.lockable metallic cabinets,2No. Wooden Desks,2No. Wooden Arm Chairs,Water harvesting goods (10,,000Ltrs Water Tank and base),40 No. Kiddy chairs and 20. No. Kiddy tables,Play equipment 4 piece set (double swing, slide, climbing frame and double see- saw),Display soft board and Branding, Publicity and Signwriting

Budget & Expenditure
Approved
KES 3.60M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1413
  • WardIvingoni/Nzambani
  • Sub-CountyKibwezi East
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 05 Sep 2024
Approved Requisition
Phase Two · 16 Sep 2024
Refloated
Phase One · 16 Oct 2024
Awarded
Phase Two · 17 Feb 2025
Site Handover
Phase Three · 26 Feb 2025
Not Started
Phase Three · 26 Feb 2025
Ongoing
Phase Three · 03 Mar 2025
Completed
Phase Three · 19 May 2025