Mechanical Road Opening And Widening

Completed GoMC-PMTS-2024-5380
Project Description

Mechanical road opening and widening of Kavuthu- A.I.C Kiioi road 5.5km and Kwa Vutu- Yumbani road 6.7Km

Budget & Expenditure
Approved
KES 2.97M
Contract
KES 2.85M
Spent
KES 2.70M
Utilisation
91%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5380
  • WardMbitini
  • Sub-CountyMakueni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start21 Mar 2024
  • End20 May 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 18 Feb 2024
Floated
Phase Two · 07 Feb 2024
Awarded
Phase Two · 12 Mar 2024
Site Handover
Phase Three · 20 Mar 2024
Not Started
Phase Two · 20 Mar 2024
Ongoing
Phase Three · 21 Mar 2024
Completed
Phase Three · 27 Jun 2024