Installation Of An Epoxy Floor Repair

Completed GoMC-PMTS-2024-9819
Project Description

Installation of an Epoxy floor repair

Budget & Expenditure
Approved
KES 1.28M
Contract
KES 0.00
Spent
KES 1.28M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9819
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateMakueni Fruit Develoment and Marketing Authority
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 05 Oct 2024
Approved Requisition
Phase Two · 30 Dec 2014
Floated
Phase Two · 30 Dec 2024
Awarded
Phase Two · 06 Jan 2025
Site Handover
Phase Three · 06 Jan 2025
Not Started
Phase Three · 06 Jan 2025
Ongoing
Phase Three · 10 Jan 2025
Completed
Phase Three · 28 Jan 2025