Agriculture Mechanzation Services(ams)

Completed GoMC-PMTS-2024-7301
Project Description

farm ponds rehabilitation - Provision of mechanization services

Budget & Expenditure
Approved
KES 1.00M
Contract
KES 360.0K
Spent
KES 500.0K
Utilisation
50%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7301
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateAgriculture
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start11 Nov 2024
  • End11 Nov 2024
Timeline
Cabinet Paper Approved
Phase One · 27 Sep 2024
Approved Requisition
Phase Two · 04 Oct 2024
Floated
Phase Two · 10 Oct 2024
Awarded
Phase Two · 11 Nov 2024
Site Handover
Phase Three · 11 Nov 2024
Not Started
Phase Two · 11 Nov 2024
Ongoing
Phase Three · 11 Nov 2024
Completed
Phase Three · 20 Dec 2024