Heavy Grading, Construction Protection Works And Installation Of Culverts At Kwa Ikavi-musoa Coffee Factory-kyaviti Drift-uuta-kwa Solo-mulooni-kyanzuki-muthwani-kanoto Road.

Completed GoMC-PMTS-2024-4522
Project Description
  • Non-vented Reinforced Concrete Drift construction
  • Cut off drains for road run off harvesting
  • Culverts Installation
  • Gabions Installation
Budget & Expenditure
Approved
KES 6.86M
Contract
KES 6.70M
Spent
KES 4.75M
Utilisation
69.2%
Budget Utilisation
Gallery (5 photos)
Kyaviti Drift
Kyaviti Drift
 Before Construction Of Kyaviti Drift In Tulimani
Before Construction Of Kyaviti Drift In Tulimani
After The Construction Of Kyaviti Drift -45m Long By 6m Wide Excavation-tulimani Ward
After The Construction Of Kyaviti Drift -45m Long By 6m Wide
Road Grading Along Kwa Solo- Uuta -kyaviti Road
Road Grading Along Kwa Solo- Uuta -kyaviti Road
Kyaviti Drift
Kyaviti Drift
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4522
  • WardTulimani
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start23 Feb 2024
  • End24 May 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 07 Dec 2023
Floated
Phase Two · 15 Dec 2023
Awarded
Phase Two · 15 Feb 2024
Site Handover
Phase Three · 23 Feb 2024
Not Started
Phase Two · 23 Feb 2024
Ongoing
Phase Three · 26 Feb 2024
Completed
Phase Three · 22 Apr 2024