Uvete Market Shed (construction Of Worktops, Compartments)

Completed GoMC-PMTS-2024-2230
Project Description

proposed upgrading of uvete market shed structure,24 No. work tops - substructure work, cubicles work tops roofing finishes

Budget & Expenditure
Approved
KES 2.00M
Contract
KES 1.89M
Spent
KES 1.89M
Utilisation
94.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2230
  • WardMukaa
  • Sub-CountyKilome
  • DepartmentDepartment of Trade, Marketing, Industry, Culture
  • DirectorateTrade
  • FY2024/2025
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start28 Feb 2025
  • End28 Apr 2025
Timeline
Cabinet Paper Approved
Phase One · 17 Jan 2025
Approved Requisition
Phase Two · 24 Jan 2025
Floated
Phase Two · 05 Feb 2025
Awarded
Phase Two · 28 Mar 2025
Site Handover
Phase Three · 28 Feb 2025
Not Started
Phase Three · 28 Feb 2025
Ongoing
Phase Three · 28 Feb 2025
Completed
Phase Three · 11 Jun 2025