Road Improvement Programme

Completed GoMC-PMTS-2024-6122
Project Description

Mechanical Road widening and heavy grading of 9Kms  on selected roads ie  Ikundu- Kwa male - kwa Maingi Thwake road, Malili -Kuku-Thwake road, Kwa Chief Ndiku- Mwaani- Kingathuni road, Malatani - Miseleni -kwa kianga road, Nguumo- MBA road.
Non vented masonry drift-25m by 5m and 35m by 5m and installation of culverts 16m by 600mm DIA along Matalani - Miseleleni - Kwa Kianga road.

Budget & Expenditure
Approved
KES 7.18M
Contract
KES 7.18M
Spent
KES 6.30M
Utilisation
87.7%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6122
  • WardKako/Waia
  • Sub-CountyMbooni
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateInfrastructure, Transport and Public works
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start15 Apr 2024
  • End14 Jul 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Sep 2023
Approved Requisition
Phase Two · 18 Jan 2024
Floated
Phase Two · 02 Sep 2024
Awarded
Phase Two · 28 Mar 2024
Site Handover
Phase Three · 10 Apr 2024
Not Started
Phase Two · 10 Apr 2024
Ongoing
Phase Three · 20 Apr 2024
Completed
Phase Three · 10 Jun 2024