Old Mukuyuni Marikiti Market

Completed GoMC-PMTS-2024-6565
Project Description

Renovation of old Mukuyuni Marikiti market

Budget & Expenditure
Approved
KES 1.00M
Contract
KES 1,000.0K
Spent
KES 1.00M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6565
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateWote Municipality
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start18 Dec 2024
  • End18 Feb 2025
Timeline
Cabinet Paper Approved
Phase One · 30 Aug 2024
Approved Requisition
Phase Two · 11 Sep 2024
Floated
Phase Two · 11 Oct 2024
Awarded
Phase Two · 10 Dec 2024
Site Handover
Phase Three · 18 Dec 2024
Not Started
Phase Two · 18 Dec 2024
Ongoing
Phase Three · 06 Jan 2025
Completed
Phase Three · 02 Dec 2024