Construction Of Modern Toilet At Kalamba - Construction Of 5 Door Wc With Urinal, Septic, Water Tank

Completed GoMC-PMTS-2024-5953
Budget & Expenditure
Approved
KES 2.30M
Contract
KES 2.30M
Spent
KES 2.30M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5953
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateWote Municipality
  • FY2024/2025
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start16 Dec 2024
  • End12 Mar 2025
Timeline
Cabinet Paper Approved
Phase One · 18 Aug 2024
Approved Requisition
Phase Two · 11 Sep 2024
Floated
Phase Two · 11 Nov 2024
Awarded
Phase Two · 10 Dec 2024
Site Handover
Phase Three · 10 Dec 2024
Not Started
Phase Two · 10 Dec 2024
Ongoing
Phase Three · 17 Dec 2024
Completed
Phase Three · 17 May 2025