Kikome Irrigation Scheme

Completed GoMC-PMTS-2024-3539
Project Description

. Operationalization of Kikome Irrigation scheme sump tank & galleries,  3 distribution line,rehabilitation distribution tank

Budget & Expenditure
Approved
KES 7.93M
Contract
KES 0.00
Spent
KES 7.00M
Utilisation
88.2%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-3539
  • WardKitise/Kithuki
  • Sub-CountyMakueni
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateCooperative Development
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
Timeline
Completed
Phase Three · 12 Dec 2024