Kiumi Water Project

Completed GoMC-PMTS-2024-9104
Project Description

 Replacement of  the PVC pipes with GI (Metallic pipes)

Budget & Expenditure
Approved
KES 64.3K
Contract
KES 3.80M
Spent
KES 3.42M
Utilisation
100%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-9104
  • WardKithungo/Kitundu
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
  • Start12 Jan 2024
  • End12 Feb 2024
Timeline
Cabinet Paper Approved
Phase One · 04 Sep 2023
Approved Requisition
Phase Two · 15 Sep 2023
Floated
Phase Two · 02 Oct 2023
Awarded
Phase Two · 31 Oct 2023
Site Handover
Phase Three · 11 Jan 2024
Not Started
Phase Two · 11 Jan 2024
Ongoing
Phase Three · 11 Jan 2024
Completed
Phase Three · 12 Feb 2024
Completed
Phase Three · 12 Feb 2024