Kwa Malombe Earth Dam

Completed GoMC-PMTS-2024-6676
Budget & Expenditure
Approved
KES 1.98M
Contract
KES 1.69M
Spent
KES 1.69M
Utilisation
85.5%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6676
  • WardKikumini/Muvau
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start24 Feb 2023
  • End25 Apr 2023
Timeline
Cabinet Paper Approved
Phase One · 22 Dec 2022
Approved Requisition
Phase Two · 16 Jan 2023
Floated
Phase Two · 26 Jan 2023
Awarded
Phase Two · 23 Feb 2023
Site Handover
Phase Three · 23 Feb 2023
Not Started
Phase Two · 23 Feb 2023
Ongoing
Phase Three · 24 Feb 2023
Completed
Phase Three · 25 Apr 2023
Completed
Phase Three · 25 Apr 2023