Distribution Of Kyandumbi Water

Completed GoMC-PMTS-2024-7786
Project Description

Drilling and Development of Kyandumbi replacement Borehole, Equipping and distribution.

Budget & Expenditure
Approved
KES 3.50M
Contract
KES 1.80M
Spent
KES 1.80M
Utilisation
51.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7786
  • WardKee
  • Sub-CountyKaiti
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start03 Jun 2024
  • End03 Jul 2024
Timeline
Cabinet Paper Approved
Phase One · 25 Mar 2024
Approved Requisition
Phase Two · 26 Mar 2024
Floated
Phase Two · 12 Apr 2024
Awarded
Phase Two · 29 May 2024
Site Handover
Phase Three · 06 Jun 2024
Not Started
Phase Two · 06 Jun 2024
Ongoing
Phase Three · 06 Jun 2024
Completed
Phase Three · 10 Dec 2024