Masyonyeki Earth Dam

Completed GoMC-PMTS-2024-2169
Budget & Expenditure
Approved
KES 4.90M
Contract
KES 4.75M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-2169
  • WardTulimani
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start19 May 2024
  • End18 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 20 Dec 2023
Approved Requisition
Phase Two · 08 Jan 2024
Floated
Phase Two · 19 Feb 2024
Awarded
Phase Two · 18 May 2024
Site Handover
Phase Three · 19 May 2024
Not Started
Phase Two · 19 May 2024
Ongoing
Phase Three · 20 May 2024
Completed
Phase Three · 26 Jun 2024