Kyunguni Earth Dam
Home
Projects
Detail
Completed
Flagship
GoMC-PMTS-2024-7091
Print
Share
Budget & Expenditure
Approved
KES 2.19M
Contract
KES 2.06M
Spent
KES 2.06M
Utilisation
94.2%
Budget Utilisation
Citizen Feedback
Name
Contact
Subject
*
Message
*
Attachment
(optional — image or PDF, max 5MB)
Submit
Project Details
Ref
GoMC-PMTS-2024-7091
Ward
Kiima Kiu/Kalanzoni
Sub-County
Kilome
Department
Department of Water and Sanitation
Directorate
Water and Sanitation
FY
2023/2024
Source
Exchequer
Funded From
Ward
Category
Flagship
Start
29 Jun 2023
End
30 Sep 2023
Timeline
Cabinet Paper Approved
Phase One · 04 May 2023
Approved Requisition
Phase Two · 19 May 2023
Floated
Phase Two · 08 Jun 2023
Awarded
Phase Two · 21 May 2023
Site Handover
Phase Three · 22 May 2023
Not Started
Phase Two · 22 Jun 2023
Ongoing
Phase Three · 29 Jun 2023
Completed
Phase Three · 11 Oct 2023
Related Projects
Yekanga Borehole - Drilling,equipping And Distribution
Ongoing
Mulala Primary Borehole - Borehole Drilling And Develop
Ongoing
Water Improvement Program -kee
Ongoing
Water Improvement Program- Mavindini
Under Procurement