Mulasya Ecde

Completed GoMC-PMTS-2024-5057
Project Description
  • 2No. ECDE Classrooms with an office and Store
  • Electrical Works (conduits only)
  • Shelves
  • 2No. Wooden Desks
  • 2No. Wooden Arm Chairs
  • Water harvesting goods (5,000Ltrs Water Tank)
  • Play equipment - 4 piece set (double swing, slide, climbing frame and double see-saw)
  • Display Pinned board
  • Branding, Publicity and Signwriting
  • 2 No. Black board retained
  • 4 No. Duster
  • 20 No. Mark pens
  • 2 No, Whiteboard
Budget & Expenditure
Approved
KES 3.14M
Contract
KES 2.99M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5057
  • WardKisau/Kiteta
  • Sub-CountyMbooni
  • DepartmentDepartment of ICT, Education and Internship
  • DirectorateECDE, Support to Education and Library Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start22 Apr 2024
  • End22 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 15 Oct 2023
Approved Requisition
Phase Two · 18 Oct 2023
Floated
Phase Two · 14 Mar 2024
Awarded
Phase Two · 22 Apr 2024
Site Handover
Phase Three · 22 Apr 2024
Not Started
Phase Two · 22 Apr 2024
Ongoing
Phase Three · 31 May 2024
Completed
Phase Three · 02 May 2025