Desilting Of Mitooni Earthdam In Kitise Kithuki Ward

Completed GoMC-PMTS-2024-7729
Budget & Expenditure
Approved
KES 1.49M
Contract
KES 1.42M
Spent
KES 997.1K
Utilisation
66.9%
Budget Utilisation
Citizen Feedback
Mayor Wa Kathonzweni 06 Jul 2024
Desilting Of Mitooni Earthdam In Kitise Kithuki Ward

That Project Has Been Indicated To Be In Kitise Kithuki Ward And Not Kathonzweni Ward

Official Response:

The project is in Kitise/Kithuki Ward. Thank you

Project Details
  • RefGoMC-PMTS-2024-7729
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start31 Jul 2023
  • End31 Aug 2023
Timeline
Cabinet Paper Approved
Phase One · 06 May 2023
Approved Requisition
Phase Two · 19 May 2023
Refloated
Phase One · 26 May 2023
Awarded
Phase Two · 07 Jun 2023
Site Handover
Phase Three · 22 Jun 2023
Not Started
Phase Two · 22 Jun 2023
Ongoing
Phase Three · 29 Jul 2023
Completed
Phase Three · 02 Aug 2023