Drilling And Develovement Of Kiteei Mutini Bh

Completed GoMC-PMTS-2024-4439
Project Description

DRILLING AND DEVELOPMENT OF BOREHOLE

Budget & Expenditure
Approved
KES 2.84M
Contract
KES 2.84M
Spent
KES 1.40M
Utilisation
49.3%
Budget Utilisation
Gallery (1 photos)
Kiteei Mutini Lowering Of Pump And Boreholes Accessories
Kiteei Mutini Lowering Of Pump And Boreholes Accessories
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-4439
  • WardKathonzweni
  • Sub-CountyMakueni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start04 Jun 2024
  • End20 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 16 May 2024
Approved Requisition
Phase Two · 21 May 2024
Floated
Phase Two · 29 May 2024
Awarded
Phase Two · 06 Jun 2024
Site Handover
Phase Three · 07 Jun 2024
Not Started
Phase Two · 10 Jun 2024
Ongoing
Phase Three · 10 Jun 2024
Completed
Phase Three · 07 May 2025