Mulima Water Project

Completed Flagship GoMC-PMTS-2024-5964
Project Description

i.Trainig of the community on management.

ii.Mobilization of personal plant and equipment to site.

iii.Implementation of treatment works components and chemical building.

Budget & Expenditure
Approved
KES 10.18M
Contract
KES 7.47M
Spent
KES 7.47M
Utilisation
73.4%
Budget Utilisation
Components (1)
Component Budget Expenditure Status
Treatment works KES 9.80M KES 0.00 Null
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-5964
  • WardMbooni
  • Sub-CountyMbooni
  • DepartmentDepartment of Water and Sanitation
  • DirectorateWater and Sanitation
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryFlagship
  • Start07 Oct 2024
  • End10 Dec 2024
Timeline
Cabinet Paper Approved
Phase One · 16 May 2024
Approved Requisition
Phase Two · 21 May 2024
Floated
Phase Two · 28 May 2024
Awarded
Phase Two · 28 Jun 2024
Site Handover
Phase Three · 30 Jun 2024
Not Started
Phase Two · 30 Jun 2024
Ongoing
Phase Three · 12 Jul 2024
Completed
Phase Three · 29 Nov 2024