Development Of Farm Ponds- Fuel

Completed GoMC-PMTS-2024-7282
Project Description

Funds used purchase fuel and repair of backhoe for farm ponds excavation. Targetting 60 farmponds per households( the project provides fuel and the farmer pays ksh3500 per hour on dry rate  ) the activities is implemented during dry spell.

Budget & Expenditure
Approved
KES 1.41M
Contract
KES 0.00
Spent
KES 500.0K
Utilisation
35.4%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7282
  • WardUkia
  • Sub-CountyKaiti
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateAgriculture
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 06 Feb 2024
Cabinet Paper Approved
Phase One · 06 Feb 2024
Approved Requisition
Phase Two · 19 Feb 2024
Ongoing
Phase Three · 12 May 2024
Completed
Phase Three · 12 Oct 2024