Construction Of Pwd Empowered Structures At Kalulini Health Centre

Completed GoMC-PMTS-2024-7416
Project Description

Construction of PWD friendly toilet, walkways and ramp

Budget & Expenditure
Approved
KES 980.0K
Contract
KES 947.8K
Spent
KES 946.6K
Utilisation
96.6%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7416
  • WardKikumbulyu South
  • Sub-CountyKibwezi West
  • DepartmentDepartment of Health Services
  • DirectorateCurative and Rehabilitative Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start13 Jan 2024
  • End14 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 02 Nov 2023
Approved Requisition
Phase Two · 01 Dec 2023
Floated
Phase Two · 01 Dec 2023
Awarded
Phase Two · 12 Jan 2024
Site Handover
Phase Three · 16 Jan 2024
Not Started
Phase Two · 16 Jan 2024
Ongoing
Phase Three · 20 Jan 2024
Completed
Phase Three · 19 Jun 2024