Mbooni – Kee Municipality

Completed GoMC-PMTS-2024-8467
Project Description

Establishment of Municipality 

  • Preparation of inception report 
  • Drafting of Municipal charter 
  • Public participation 
  • Delineation for proposed Municipality 
Budget & Expenditure
Approved
KES 4.00M
Contract
KES 2.78M
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-8467
  • WardAll Wards
  • Sub-CountyMbooni
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateMbooni - Kee Municipality
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start02 Jul 2024
  • End30 Aug 2024
Timeline
Cabinet Paper Approved
Phase One · 07 May 2024
Approved Requisition
Phase Two · 09 May 2024
Floated
Phase Two · 21 May 2024
Awarded
Phase Two · 25 Jun 2024
Site Handover
Phase Three · 27 Jun 2024
Not Started
Phase Two · 27 Jun 2024
Ongoing
Phase Three · 27 Jun 2024
Completed
Phase Three · 26 Aug 2024