Puree Production

Completed GoMC-PMTS-2024-7096
Project Description

production of puree 

Budget & Expenditure
Approved
KES 13.55M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7096
  • WardHeadquaters
  • Sub-CountyHeadquarters
  • DepartmentDepartment of Agriculture, Livestock, Fisheries &
  • DirectorateMakueni Fruit Develoment and Marketing Authority
  • FY2023/2024
  • SourceExchequer
  • Funded FromHeadquarters
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 07 Sep 2023
Approved Requisition
Phase Two · 03 Oct 2023
Ongoing
Phase Three · 20 Dec 2023
Completed
Phase Three · 08 Feb 2023