Control Of Gulleys At Kwe Kuyu Kalembwani
Home
Projects
Detail
Completed
GoMC-PMTS-2024-1796
Print
Share
Project Description
Excavation
Concrete works and protection works
Budget & Expenditure
Approved
KES 1.00M
Contract
KES 998.3K
Spent
KES 998.3K
Utilisation
99.8%
Budget Utilisation
Citizen Feedback
Name
Contact
Subject
*
Message
*
Attachment
(optional — image or PDF, max 5MB)
Submit
Project Details
Ref
GoMC-PMTS-2024-1796
Ward
Kiima Kiu/Kalanzoni
Sub-County
Kilome
Department
Department of Lands, Urban Planning and Developmen
Directorate
Environment and Climate Change
FY
2023/2024
Source
Exchequer
Funded From
Ward
Category
Non Flagship
Start
04 Mar 2024
End
01 Apr 2024
Timeline
Cabinet Paper Approved
Phase One · 22 Aug 2023
Approved Requisition
Phase Two · 22 Sep 2023
Floated
Phase Two · 30 Nov 2023
Awarded
Phase Two · 22 Feb 2024
Site Handover
Phase Three · 04 Mar 2024
Not Started
Phase Two · 04 Mar 2024
Ongoing
Phase Three · 04 Mar 2024
Completed
Phase Three · 17 Apr 2024
Related Projects
Desilting Of Londokwe Earth Dam
Under Procurement
Sekeleni Integrated Water Project
Ongoing
570-grid Powered Streetlights And Floodlights
Completed
Kilisa & Athitunguni Distribution And Livelihood Projec
Under Procurement