Purchase Of Tanks

Completed GoMC-PMTS-2024-6078
Project Description

Purchase and supply of 3 of water tanks

Budget & Expenditure
Approved
KES 451.8K
Contract
KES 398.7K
Spent
KES 398.7K
Utilisation
88.3%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-6078
  • WardNzaui/Kilili/Kalamba
  • Sub-CountyMakueni
  • DepartmentDepartment of Health Services
  • DirectoratePreventive and Promotive Services
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start27 Jun 2024
  • End26 Jul 2024
Timeline
Cabinet Paper Approved
Phase One · 30 May 2024
Approved Requisition
Phase Two · 03 Jun 2024
Floated
Phase Two · 02 Jun 2024
Awarded
Phase Two · 26 Jun 2024
Site Handover
Phase Three · 27 Jun 2024
Not Started
Phase Two · 27 Jun 2024
Ongoing
Phase Three · 27 Jun 2024
Completed
Phase Three · 24 Jul 2024