Electrification Of Usalama Market(matching Grant)

Completed GoMC-PMTS-2024-1918
Project Description

Installation of transformers, construction of HV lines, construction of distribution lv lines networks to house holds,Public institutions/facilities and churches. 

Budget & Expenditure
Approved
KES 1.50M
Contract
KES 0.00
Spent
KES 0.00
Utilisation
0%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-1918
  • WardThange
  • Sub-CountyKibwezi East
  • DepartmentDepartment of Infrastructure, Transport, Public Wo
  • DirectorateEnergy
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
Timeline
Cabinet Paper Approved
Phase One · 27 Aug 2023
Approved Requisition
Phase Two · 18 Oct 2023
Ongoing
Phase Three · 18 Oct 2023
Completed
Phase Three · 09 Sep 2024