Rehabilitation of gulleys and road bush clearing and drainage

Completed GoMC-PMTS-2024-7822
Project Description

Rehabilitation and repair of Kee Matwiku Gulley 

  • Excavation and filing of structures
  • Culverts and drainage works
  • Health, Safety and Environment (H.S.E)

 

Budget & Expenditure
Approved
KES 500.0K
Contract
KES 494.5K
Spent
KES 494.5K
Utilisation
98.9%
Budget Utilisation
Citizen Feedback
Project Details
  • RefGoMC-PMTS-2024-7822
  • WardKee
  • Sub-CountyKaiti
  • DepartmentDepartment of Lands, Urban Planning and Developmen
  • DirectorateEnvironment and Climate Change
  • FY2023/2024
  • SourceExchequer
  • Funded FromWard
  • CategoryNon Flagship
  • Start23 May 2024
  • End28 Jun 2024
Timeline
Cabinet Paper Approved
Phase One · 16 Feb 2024
Approved Requisition
Phase Two · 19 Feb 2024
Floated
Phase Two · 12 Mar 2024
Awarded
Phase Two · 09 Apr 2024
Site Handover
Phase Three · 16 Apr 2024
Not Started
Phase Two · 16 Apr 2024
Ongoing
Phase Three · 28 May 2024
Completed
Phase Three · 14 Jun 2024